Roads19FB0011

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS: BATAN ISLAND CIRCUMFERENTIAL ROAD, ALBAY

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS: BATAN ISLAND CIRCUMFERENTIAL ROAD, ALBAY is a DPWH-tracked public work in Albay 2nd DEO, Region V. Reported contract value: ₱28,417,834.47. Status: Past target date (DPWH On-Going). Contractor on record: SUNWEST INC FORMERLY: SUNWEST CONST. Figures trace to dpwh.

Albay 2nd DEO, Region V
Region: Region V

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROXI-19-0019722

₱241,576.00 · FY2019

Released to Division of Davao del Norte (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

738 projects · ₱73.0B total · 0 flags

Other projects by this contractor

No sat.

CLUSTER 1: BASIC INFRASTRUCTURE PROGRAM (BIP) - COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION - CONSTRUCTION OF CAUSEWAY, SUBSECTION 3.2A, TACLOBAN CITY, LEYTE ; AND OTHER FIVE (5) PROJECTS

Region VIII, Region VIII

2024₱1.3B
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF STORM SURGE PROTECTION/TIDE EMBANKMENT, LEYTE

Region VIII, Region VIII

2023₱1.1B
Past target date (DPWH On-Going)
No sat.

CLUSTER 2: PROJECT 1. CONST. OF CAUSEWAY, SECT. 3.1, STA. 0+140-STA. 0+233, TAC. CITY, LEYTE; PROJECT 2. CONST. OF CAUSEWAY, SECT. 3.2, STA. 0+233-STA.0+305, TAC. CITY, LEYTE; PROJECT 3. CONST. OF CAUSEWAY, SECT. 3.3, STA. 0+400-STA. 0+448, TAC. CITY, LEY

Region VIII, Region VIII

2022₱511.9M
Past target date (DPWH On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM- CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF ROAD DIKE MUMPONG RIVER, TUBAN-BATONG BUHAY, BRGY. TUBAN, SABLAYAN, OCC. MINDORO

Region IV-B, Region IV-B

2025₱291.8M
Past target date (DPWH On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM- CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF ROAD DIKE, MUMPONG RIVER, TUBAN-STA. LUCIA, BRGY. TUBAN, SABLAYAN, OCC. MINDORO

Region IV-B, Region IV-B

2025₱291.5M
Past target date (DPWH On-Going)

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-INTERJURISDICTIONAL ROADS AND/OR BRIDGES(OR, ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS)-CONSTRUCTION OF ROAD,MIISI-BONGA-BUYUAN-LIDONG-DARAGA,DARAGA/

Region V, Region V

2022₱288.5M
Reported complete (100% progress, DPWH status On-Going)
View all 738 projects →

4. Implementation

Contract Amount

₱28,417,834.47

Progress

Past target date (DPWH On-Going)

Start Date

May 22, 2019

Target End

October 19, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.