Construction of Flood Mitigation Structure23NH0003

Construction of Flood Control Structure along Tago River, Brgy. Libas Gua, San Miguel, Surigao del Sur

Construction of Flood Control Structure along Tago River, Brgy. Libas Gua, San Miguel, Surigao del Sur is a DPWH-tracked public work in TAGO (SURIGAO DEL SUR), SURIGAO DEL SUR, Region XIII. Reported contract value: ₱48,999,999.94. Status: Reported complete (DPWH). Contractor on record: LCTING CONST AND DEVELOPMENT CORP FORMERLY: L C TING CONST. Figures trace to sumbong.

TAGO (SURIGAO DEL SUR), SURIGAO DEL SUR, Region XIII
Region: Region XIII

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Tago River, Brgy. Libas Gua, San Miguel, Surigao del Sur
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Surigao del Sur 1st District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

304 projects · ₱17.1B total · 2 flags

4. Implementation

Contract Amount

₱48,999,999.94

Progress

Reported complete (DPWH)

Start Date

April 4, 2023

Target End

December 15, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.