Buildings and Facilities18FC0202

COMPLETION OF TWO (2) STOREY FOUR (4) LABORATORY (SCIENCE AND ICT), PARACALE NHS, PARACALE CAMS, NOR

COMPLETION OF TWO (2) STOREY FOUR (4) LABORATORY (SCIENCE AND ICT), PARACALE NHS, PARACALE CAMS, NOR is a DPWH-tracked public work in Camarines Norte DEO, Region V. Reported contract value: ₱3,508,358.97. Status: Reported complete (DPWH). Contractor on record: O L DE LEON CONST. Figures trace to dpwh.

Camarines Norte DEO, Region V
Region: Region V

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Capalonga River Control Structure, Binawangan Section, Capalonga, Camarines Norte
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROV-18-0032622

₱0.00 · FY2018

Released to Division of Camarines Sur (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱3,508,358.97

Progress

Reported complete (DPWH)

Start Date

December 10, 2018

Target End

June 21, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.