Flood Control and Drainage22EH0055

CONSTRUCTION OF PANANGCALAN FLOOD CONTROL STRUCTURE (DOWNSTREAM), STA. 0+080.00 - STA. 0+160.00 (L/S), STA. 0+080.00 - STA. 0+164.00 (R/S), SAN FERNANDO, ROMBLON

CONSTRUCTION OF PANANGCALAN FLOOD CONTROL STRUCTURE (DOWNSTREAM), STA. 0+080.00 - STA. 0+160.00 (L/S), STA. 0+080.00 - STA. 0+164.00 (R/S), SAN FERNANDO, ROMBLON is a DPWH-tracked public work in Romblon DEO, Region IV-B. Reported contract value: ₱24,299,425.49. Status: Reported complete (DPWH). Contractor on record: MGM PADOR CORP FORMERLY: MA GINA M PADOR CONST. Figures trace to dpwh.

Romblon DEO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

Probable match · score 90%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Panangcalan Flood Control Structure (Downstream), San Fernando, Romblon
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Romblon DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

39 projects · ₱666.9M total · 0 flags

4. Implementation

Contract Amount

₱24,299,425.49

Progress

Reported complete (DPWH)

Start Date

April 6, 2022

Target End

October 25, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.