GAA 2025 OO-225IG0067

CONSTRUCTION OF SALOG FLOOD CONTROL STRUCTURE AT (DOWNSTREAM SECTION), HILONGOS, LEYTE

CONSTRUCTION OF SALOG FLOOD CONTROL STRUCTURE AT (DOWNSTREAM SECTION), HILONGOS, LEYTE is a DPWH-tracked public work in Leyte 5th DEO, Region VIII. Reported contract value: ₱53,050,500.00. Status: Past target date (DPWH On-Going). Contractor on record: KOUZBARY BUILDERS. Figures trace to dpwh.

Leyte 5th DEO, Region VIII
Region: Region VIII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱60,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Limbuhan River, Barangay Cantariwis, Tolosa, Leyte
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Leyte 5th DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

95 projects · ₱8.3B total · 0 flags

4. Implementation

Contract Amount

₱53,050,500.00

Progress

Past target date (DPWH On-Going)

Start Date

July 22, 2025

Target End

April 8, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.