Construction of Flood Mitigation Structure24EA0027

Construction of Santol Flood Control, Boac, Marinduque

Construction of Santol Flood Control, Boac, Marinduque is a DPWH-tracked public work in BOAC (CAPITAL) (MARINDUQUE), MARINDUQUE, Region IV-B. Reported contract value: ₱18,214,714.08. Status: Reported complete (DPWH). Contractor on record: JEDIDIAH CONST. Figures trace to sumbong.

BOAC (CAPITAL) (MARINDUQUE), MARINDUQUE, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Santol Flood Control, Boac, Marinduque
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0008376

₱1,513,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0008387

₱140,000.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱18,214,714.08

Progress

Reported complete (DPWH)

Start Date

January 30, 2024

Target End

July 10, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.