Roads25N00246

CONSTRUCTION OF PEDESTRIAN OVERPASS AT MAHARLIKA HIGHWAY (SURIGAO-AGUSAN SECT)- K1123+219, BRGY. LUNA, SURIGAO CITY, SURIGAO DEL NORTE

CONSTRUCTION OF PEDESTRIAN OVERPASS AT MAHARLIKA HIGHWAY (SURIGAO-AGUSAN SECT)- K1123+219, BRGY. LUNA, SURIGAO CITY, SURIGAO DEL NORTE is a DPWH-tracked public work in Region XIII, Region XIII. Reported contract value: ₱35,322,286.78. Status: Past target date (DPWH On-Going). Contractor on record: JMT CONST. Figures trace to dpwh.

Region XIII, Region XIII
Region: Region XIII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2025 GAA. DBM GAA FY2025

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱35,322,286.78

Progress

Past target date (DPWH On-Going)

Start Date

August 28, 2025

Target End

March 25, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.