Flood Control and Drainage19CL0016

CONSTRUCTION OF SLOPE PROTECTION / FLOOD CONTROL (BANCAL RIVER DOWNSTREAM NORTH APPROACH), IBA, ZAMBALES, PHASE IV

CONSTRUCTION OF SLOPE PROTECTION / FLOOD CONTROL (BANCAL RIVER DOWNSTREAM NORTH APPROACH), IBA, ZAMBALES, PHASE IV is a DPWH-tracked public work in Zambales 1st DEO, Region III. Reported contract value: ₱44,469,120.67. Status: Reported complete (DPWH). Contractor on record: STO CRISTO CONST. Figures trace to dpwh.

Zambales 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROVII-19-0015536

₱9,465,352.00 · FY2019

Released to Zambales 1st DEO (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

490 projects · ₱18.9B total · 0 flags

Other projects by this contractor

View all 490 projects →

4. Implementation

Contract Amount

₱44,469,120.67

Progress

Reported complete (DPWH)

Start Date

June 21, 2019

Target End

January 16, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.