Flood Control and Drainage19DN0178

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG TAYTAY RIVER, TAYTAY, RIZAL

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG TAYTAY RIVER, TAYTAY, RIZAL is a DPWH-tracked public work in Rizal 1st DEO, Region IV-A. Reported contract value: ₱17,186,701.02. Status: Reported complete (DPWH). Contractor on record: A J LAVA BUILDERS CORP FORMERLY: A J LAVA BUIL. Figures trace to dpwh.

Rizal 1st DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXIII-19-0013190

₱1,790,228.00 · FY2019

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱17,186,701.02

Progress

Reported complete (DPWH)

Start Date

July 22, 2019

Target End

December 18, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.