Rehabilitation / Major Repair of Flood Control Structure24IA0088

Rehabilitation of Anas Flood Control Structure, Phase 3, barangay Atipolo, Naval, Biliran

Rehabilitation of Anas Flood Control Structure, Phase 3, barangay Atipolo, Naval, Biliran is a DPWH-tracked public work in NAVAL (CAPITAL) (BILIRAN), BILIRAN, Region VIII. Reported contract value: ₱19,595,819.67. Status: Reported complete (DPWH). Contractor on record: LCTING CONST AND DEVELOPMENT CORP FORMERLY: L C TING CONST. Figures trace to sumbong.

NAVAL (CAPITAL) (BILIRAN), BILIRAN, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Anas Flood Control Structure, Phase 3, barangay Atipolo, Naval, Biliran
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-24-0008479

₱1,467,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-24-0002253

₱1,340,225.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-24-0001232

₱289,442.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-24-0008480

₱135,000.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

304 projects · ₱17.1B total · 2 flags

4. Implementation

Contract Amount

₱19,595,819.67

Progress

Reported complete (DPWH)

Start Date

March 13, 2024

Target End

August 4, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.