Flood Control and Drainage19OB0262

IMPROVEMENT OF NANGKA RIVER, RED CROSS COMPOUND, MARIKINA CITY

IMPROVEMENT OF NANGKA RIVER, RED CROSS COMPOUND, MARIKINA CITY is a DPWH-tracked public work in Metro Manila 1st DEO, National Capital Region. Reported contract value: ₱27,497,252.41. Status: Reported complete (DPWH). Contractor on record: M3 KONSTRACT CORP FORMERLY:MARGARITA CONST. Figures trace to dpwh.

Metro Manila 1st DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIII-19-0021485

₱1,053,644.00 · FY2019

Released to Division of Nueva Ecija (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱27,497,252.41

Progress

Reported complete (DPWH)

Start Date

July 12, 2019

Target End

January 7, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.