Roads24HG0062

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS- PRIMARY ROADS - N. BACALSO AVE (CEBU SOUTH RD) - K0087+950 - K0089+100

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS- PRIMARY ROADS - N. BACALSO AVE (CEBU SOUTH RD) - K0087+950 - K0089+100 is a DPWH-tracked public work in Cebu 2nd DEO, Region VII. Reported contract value: ₱34,318,716.50. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: WTG CONST. Figures trace to dpwh.

Cebu 2nd DEO, Region VII
Region: Region VII

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Bulacao River Flood Control Structure, Talisay City, Cebu
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Cebu 2nd DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

298 projects · ₱12.8B total · 0 flags

Other projects by this contractor

CONSTRUCTION OF STORM SURGE PROTECTION: HEIGHTENED ROAD AND TIDE EMBANKMENT, STATION 1+900 - STATION 2+550, SECTION 5 PHASE 9, BRGY. SAN JOAQUIN, PALO, LEYTE

Region VIII, Region VIII

2018₱263.4M
Reported complete (DPWH)

CONSTRUCTION OF FLOOD MITIGATION FACILITIES ALONG MAJOR RIVER BASINS AND PRINCIPAL RIVERS AT SIPALAY RIVER

Region VI, Region VI

2018₱195.5M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF FLYOVERS/INTERCHANGES/UNDERPASSES/LONG SPAN BRIDGES PANGLAO-TAGBILARAN CITY OFFSHORE BRIDGE, SECTION 1: STA.000+000-STA.000+223.21, SECTION

Region VII, Region VII

2020₱193.0M
Reported complete (DPWH)
No sat.

CSSP, SUSTAINABLE INFRA PROJ. ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BLDG./ FACILITIES, CONST. OF ROAD FROM TABON TO BARANGAY GUBA LEADING TO BINAKAYAN, VALLEHERMOSO,NEGROS ORIENTAL

Region VII, Region VII

2024₱193.0M
Past target date (DPWH On-Going)
No sat.

CSSP, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG PINOCAWAN RIVER, VALLEHERMOSO, NEGROS ORIENTAL

Region VII, Region VII

2024₱193.0M
Past target date (DPWH On-Going)
No sat.

CSSP, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BATERIA RIVER, GUIHULNGAN CITY, NEGROS ORIENTAL

Region VII, Region VII

2024₱193.0M
Past target date (DPWH On-Going)
View all 298 projects →

4. Implementation

Contract Amount

₱34,318,716.50

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

April 25, 2024

Target End

September 21, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.