Buildings and Facilities17JI0004

CLUSTER 4 - CONSTRUCTION OF MULTI-PURPOSE BUILDING IN THE MUNICIPALITY OF PAYAO, ZAMBOANGA SIBUGAY

CLUSTER 4 - CONSTRUCTION OF MULTI-PURPOSE BUILDING IN THE MUNICIPALITY OF PAYAO, ZAMBOANGA SIBUGAY is a DPWH-tracked public work in Zamboanga Sibugay 1st DEO, Region IX. Reported contract value: ₱5,852,121.05. Status: Reported complete (DPWH). Contractor on record: LAKEWOOD CONST CO. Figures trace to dpwh.

Zamboanga Sibugay 1st DEO, Region IX
Region: Region IX

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱33,427,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control along Junction Imelda-Alicia Road, part of Sibuguey River, (Sta. 00+335 - Sta. 00+671 upstream), Barangay Bulawan, Payao, Zamboanga Sibugay
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIVA-17-0020611

₱82,422.00 · FY2017

Released to Batangas State University (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

Construction of MPB

₱5,852,121.05 · LAKEWOOD CONSTRUCTION

Contractor

C

98 projects · ₱1.6B total · 0 flags

4. Implementation

Contract Amount

₱5,852,121.05

Progress

Reported complete (DPWH)

Start Date

February 27, 2017

Target End

June 21, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.