GAA 2025 OO-125EH0024

PAVING OF UNPAVED ROADS ALONG SIBUYAN CIRCUMFERENTIAL ROAD, K0031+421 - K0031+461, K0031+592 - K0031+632, K0039+013 - K0039+033.40 (AS PER ACTUAL & RBIA), SIBUYAN ISLAND, ROMBLON

PAVING OF UNPAVED ROADS ALONG SIBUYAN CIRCUMFERENTIAL ROAD, K0031+421 - K0031+461, K0031+592 - K0031+632, K0039+013 - K0039+033.40 (AS PER ACTUAL & RBIA), SIBUYAN ISLAND, ROMBLON is a DPWH-tracked public work in Romblon DEO, Region IV-B. Reported contract value: ₱4,111,153.40. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: MT GUITING-GUITING CONST. Figures trace to dpwh.

Romblon DEO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱28,101,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Campalingo Flood Control Structure along Sibuyan Circumferential Road, Phase 2, Barangay Campalingo, San Fernando, Romblon
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Romblon DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

4. Implementation

Contract Amount

₱4,111,153.40

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

July 28, 2025

Target End

October 10, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.