Bridges17FA0028

CLUSTER 15- WIDENING OF PERMANENT BRIDGES TO MORE THAN 2-LANES AND REPLACEMENT OF PERMANENT WEAK BRIDGES AT TABACO CITY, ALBAY 1ST LD

CLUSTER 15- WIDENING OF PERMANENT BRIDGES TO MORE THAN 2-LANES AND REPLACEMENT OF PERMANENT WEAK BRIDGES AT TABACO CITY, ALBAY 1ST LD is a DPWH-tracked public work in Albay 1st DEO, Region V. Reported contract value: ₱24,696,000.00. Status: Reported complete (DPWH). Contractor on record: 3RB CONST. Figures trace to dpwh.

Albay 1st DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱2,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Concreting of Dike Flood Control, Barangay San Ramon, Tabaco City, Albay
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROV-17-0008992

₱35,000.00 · FY2017

Released to Tabaco National High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

36 projects · ₱895.1M total · 0 flags

4. Implementation

Contract Amount

₱24,696,000.00

Progress

Reported complete (DPWH)

Start Date

April 30, 2017

Target End

November 30, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.