Roads20NG0030

NETWORK DEVELOPMENTPROGRAM: ROAD WIDENING - PRIMARY ROADS, DAANG MAHARLIKA (SURIGAO-AGUSAN SECTION) - K1160+784.000 - K1162+084.72, K1163+600.00 - K1163+660.00/ALEGRIA, SURIGAO DEL NORTE

NETWORK DEVELOPMENTPROGRAM: ROAD WIDENING - PRIMARY ROADS, DAANG MAHARLIKA (SURIGAO-AGUSAN SECTION) - K1160+784.000 - K1162+084.72, K1163+600.00 - K1163+660.00/ALEGRIA, SURIGAO DEL NORTE is a DPWH-tracked public work in Surigao del Norte 2nd DEO, Region XIII. Reported contract value: ₱50,179,949.49. Status: Reported complete (DPWH). Contractor on record: GICAR CONST INC. Figures trace to dpwh.

Surigao del Norte 2nd DEO, Region XIII
Region: Region XIII

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Ombong Flood Control, Alegria, Surigao del Norte
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Surigao del Norte 2nd DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱50,179,949.49

Progress

Reported complete (DPWH)

Start Date

December 14, 2020

Target End

April 7, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.