Rehabilitation / Major Repair of Drainage Structure23OB0338

Upgrading of Drainage System at Jacinto St., Orellana St., Llamera St., Marinduque St., Franco St. at Barangay New Lower Bicutan, Taguig City

Upgrading of Drainage System at Jacinto St., Orellana St., Llamera St., Marinduque St., Franco St. at Barangay New Lower Bicutan, Taguig City is a DPWH-tracked public work in TAGUIG CITY (METROPOLITAN MANILA), TAGUIG CITY, National Capital Region. Reported contract value: ₱9,309,670.78. Status: Reported complete (DPWH). Contractor on record: RGDG CONST. Figures trace to sumbong.

TAGUIG CITY (METROPOLITAN MANILA), TAGUIG CITY, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱9,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Mitigation Structure, Ilugin Creek at Barangay Pinagbuhatan, Pasig City
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Metro Manila 1st District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱9,309,670.78

Progress

Reported complete (DPWH)

Start Date

June 8, 2023

Target End

December 4, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.