Buildings and Facilities17FC0193

CONST. OF TWO(2) STOREY FOUR (4) C/L SCHOOL BLDG., BALCE ELEM. SCHOOL, BASUD CAMS. NORTE

CONST. OF TWO(2) STOREY FOUR (4) C/L SCHOOL BLDG., BALCE ELEM. SCHOOL, BASUD CAMS. NORTE is a DPWH-tracked public work in Camarines Norte DEO, Region V. Reported contract value: ₱11,017,292.11. Status: Reported complete (DPWH). Contractor on record: AVZ CONST AND SUPPLY. Figures trace to dpwh.

Camarines Norte DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱40,402,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Danao River Flood Control Structure, Sta. 0+000 - Sta. 0+580 (R/S) and Sta. 0+210 - Sta. 0+580 (L/S), Brgys. Parang and Plaridel, Jose Panganiban, Camarines Norte
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROV-17-0009159

₱86,116.00 · FY2017

Released to Division of Camarines Norte (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

23 projects · ₱227.4M total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 1 (OO1): ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM-CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS-SECONDARY ROADS-DAET AIRPORT RD-K0344+941-K0345+916, DAET AIRPORT RD-K0344+94

Region V, Region V

2024₱24.1M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM(CSSP) - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) -FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES - CONSTRUCTION OF COMPREHENSIVE DRAINAGE SYSTEM OF DAET, PHASE II, DAET,

Region V, Region V

2023₱23.4M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-SIPAG- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONCRETING OF DRAINAGE SYSTEM, BRGY. LAG-ON, DAET, CAMARINES NOR

Region V, Region V

2025₱18.7M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM-TRIP)-DAET-VINZONS LEADING TO MANTIGBI-SULA-SABANG-AGUIT-IT BEACH, QUINAMANUKAN ISLAND, VINZONS,

Region V, Region V

2025₱18.7M
Past target date (DPWH On-Going)
No sat.

CONCRETING OF BRGY. PAMBUHAN FMR, BRGY. PAMBUHAN, MERCEDES CAMARINES NORTE

Camarines Norte DEO, Region V

2019₱14.5M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF ADMINISTRATION BUILDING, CAMP BUSIG-ON, BRGY. TULAY NA LUPA, LABO, CAMARINES NORTE

Camarines Norte DEO, Region V

2021₱11.2M
Reported complete (DPWH)
View all 23 projects →

4. Implementation

Contract Amount

₱11,017,292.11

Progress

Reported complete (DPWH)

Start Date

December 27, 2017

Target End

March 7, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.