Buildings and Facilities18FI0123

CONSTRUCTION OF 1-UNIT 2-STOREY 2-ICT BUILDING (9.50M X 23.00M) AT MARY PERPETUA E. BRIOSO MEM. HIGH SCHOOL, MILAGROS, MASBATE

CONSTRUCTION OF 1-UNIT 2-STOREY 2-ICT BUILDING (9.50M X 23.00M) AT MARY PERPETUA E. BRIOSO MEM. HIGH SCHOOL, MILAGROS, MASBATE is a DPWH-tracked public work in Masbate 2nd DEO, Region V. Reported contract value: ₱10,401,139.56. Status: Reported complete (DPWH). Contractor on record: GACT ENT. Figures trace to dpwh.

Masbate 2nd DEO, Region V
Region: Region V

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation/Improvement of Gahit Flood Control, Gahit, Cataingan, Masbate
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Agency-level releases for FY2018, not tied to this contract

Masbate 2nd DEO · SARO 1,489 (₱126,676,811,675.00) · NCA 1,617 (₱426,584,627,343.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

77 projects · ₱873.4M total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM- BASIC INFRASTRUCTURE PROGRAM - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD-JUNCTION NATIONAL ROAD TO BARANGAY MANAGANAGA TO BAR

Masbate 2nd DEO, Region V

2023₱49.5M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF CALASUCHE SEAWALL, MILAGROS, MASBATE

Masbate 2nd DEO, Region V

2024₱49.0M
Reported complete (DPWH)
No sat.

Construction of Flood Control Concrete Revetment at Marcella River, Upstream Leftside, Barangay Marcella, Sta. 0+000.00 - Sta. 0+165.00, Uson, Masbate

USON (MASBATE), MASBATE, Region V

2023₱39.1M
Reported complete (DPWH)
No sat.

Construction of Gaid Flood Control, Sta. 0+796.00 - Sta. 0+937.00, Upstream Left Side, Barangay Gaid, Dimasalang, Masbate

DIMASALANG (MASBATE), MASBATE, Region V

2023₱37.2M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS SECONDARY ROADS - JCT. TAWAD-BALUD RD. K0065+564 - K0065+800, BALUD, MASBATE

Masbate 2nd DEO, Region V

2023₱32.7M
Reported complete (100% progress, DPWH status On-Going)
No sat.

NETWORK DEVELOPMENT - ROAD WIDENING - SECONDARY ROADS - MASBATE - CATAINGAN - PLACER RD. (S00005MT) K0001+627 - K0001+760, K0001+779 - K0001+855, K0008+382 - K0008+723, MASBATE CITY AND MOBO, MASBATE

Masbate 2nd DEO, Region V

2020₱29.7M
Reported complete (DPWH)
View all 77 projects →

4. Implementation

Contract Amount

₱10,401,139.56

Progress

Reported complete (DPWH)

Start Date

August 14, 2018

Target End

February 9, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.