Flood Control and Drainage17LE0016

LOCALLY FUNDED PROJECTS- LOCAL INFRASTRUCTURE PROGRAM- FLOOD CONTROL AND DRAINAGE- FLOOD CONTROL STRUCTURES / FACILITIES - CONSTRUCTION OF CONCRETE REVETMENT, COLAGSING FLOOD CONTRO

LOCALLY FUNDED PROJECTS- LOCAL INFRASTRUCTURE PROGRAM- FLOOD CONTROL AND DRAINAGE- FLOOD CONTROL STRUCTURES / FACILITIES - CONSTRUCTION OF CONCRETE REVETMENT, COLAGSING FLOOD CONTRO is a DPWH-tracked public work in Davao Occidental DEO, Region XI. Reported contract value: ₱1,467,440.89. Status: Reported complete (DPWH). Contractor on record: AL HANDASA CONST. Figures trace to dpwh.

Davao Occidental DEO, Region XI
Region: Region XI

Follow the peso

3 of 5 steps linked from public records. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2017 · ₱39,000

    Possible match · score 0.82

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-BMB-D-17-0025737 · ₱6,325,000

    Possible match · score 0.61

    DBM release source ↗
  3. 3. PhilGEPS award

    Not yet linked

  4. 4. DPWH progress + satellite

    100% reported · imagery 2015-12-05 → 2025-09-28

    Same record (DPWH contract ID)

    DPWH source ↗
  5. 5. COA audit finding

    Not yet linked

Site vs flood hazard · Project NOAH 100-year map

Outside mapped flood-hazard zones · Davao Occidental

Based on the coordinates published with the DPWH record and NOAH file DavaoOccidental.zip. Pins are sometimes placed at the town center rather than the site. NOAH data (ODbL) · Need vs spending by province

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: LOCALLY FUNDED PROJECTS- LOCAL INFRASTRUCTURE PROGRAM- FLOOD CONTROL AND DRAINAGE- FLOOD CONTROL STRUCTURES / FACILITIES - CONSTRUCTION OF CONCRETE REVETMENT, COLAGSING FLOOD CONTRO

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱39,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control at Kadayawan, Matina River Section
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-D-17-0025737

₱6,325,000.00 · FY2017

Released to Iwahig Prison an Penal Farm (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱1,467,440.89

Progress

Reported complete (DPWH)

Start Date

June 19, 2017

Target End

August 31, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.