Flood Control and Drainage20JF0019

CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG TUPILAC RIVER (PHASE II), R.T. LIM, ZAMBOANGA SIBUGAY

CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG TUPILAC RIVER (PHASE II), R.T. LIM, ZAMBOANGA SIBUGAY is a DPWH-tracked public work in Zamboanga Sibugay 2nd DEO, Region IX. Reported contract value: ₱28,148,288.26. Status: Reported complete (DPWH). Contractor on record: LAKEWOOD CONST CO. Figures trace to dpwh.

Zamboanga Sibugay 2nd DEO, Region IX
Region: Region IX

Money Trail

1. Appropriation

Probable match · score 93%

UACS
18001
Amount
₱28,743,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Tupilac River (Phase II), R.T. Lim, Zamboanga Sibugay
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Zamboanga Sibugay 2nd DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

98 projects · ₱1.6B total · 0 flags

4. Implementation

Contract Amount

₱28,148,288.26

Progress

Reported complete (DPWH)

Start Date

March 20, 2020

Target End

December 18, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.