CLUSTER III-CONSTRUCTION OF RAINWATER COLLECTION SYSTEM (RWCS) 1.ABONGAN NHS,BGY. ABONGAN,TAYTAY 2.BINUAN ES,BGY. LIBERTAD TAYTAY 3.BATO CS, BGY.BATO TAYTAY 4.BATO NHS,BGY.BATO,TAYTAY 5.PORT BARTON NHS,BGY. PORT BARTON SAN VICENTE 6.MANLAG ES BGY.MANLAG

CLUSTER III-CONSTRUCTION OF RAINWATER COLLECTION SYSTEM (RWCS) 1.ABONGAN NHS,BGY. ABONGAN,TAYTAY 2.BINUAN ES,BGY. LIBERTAD TAYTAY 3.BATO CS, BGY.BATO TAYTAY 4.BATO NHS,BGY.BATO,TAYTAY 5.PORT BARTON NHS,BGY. PORT BARTON SAN VICENTE 6.MANLAG ES BGY.MANLAG is a DPWH-tracked public work in Palawan 1st DEO, Region IV-B. Reported contract value: ₱1,101,512.79. Status: Reported complete (DPWH). Contractor on record: LEA. Figures trace to dpwh.

Palawan 1st DEO, Region IV-B
Region: Region IV-B

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 72%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Flood Control Projects in Central Luzon - Rehabilitation of Slope Protection along Pampanga River, San Luis, Pampanga
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-B-16-0009500

₱72,729.00 · FY2016

Released to 000 - Philippine Commission on Women (National Com To cover (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱1,101,512.79

Progress

Reported complete (DPWH)

Start Date

July 28, 2016

Target End

August 26, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.