Roads17J00055

ROAD UPGRADING (GRAVEL TO PAVED) OF EASTERN BOBONGAN - SOMINOT - MIDSALIP - DUMINGAG ROAD, ZAMBOANGA DEL SUR, (CHAINAGE:7028-9368) K1670+440.00 - K1672+780.00, (CHAINAGE:4334-6168) K1667+746.00 - K1669+580.00, (NET LENGTH: 4,174.00 LN.M.)

ROAD UPGRADING (GRAVEL TO PAVED) OF EASTERN BOBONGAN - SOMINOT - MIDSALIP - DUMINGAG ROAD, ZAMBOANGA DEL SUR, (CHAINAGE:7028-9368) K1670+440.00 - K1672+780.00, (CHAINAGE:4334-6168) K1667+746.00 - K1669+580.00, (NET LENGTH: 4,174.00 LN.M.) is a DPWH-tracked public work in Region IX, Region IX. Reported contract value: ₱143,443,937.46. Status: Reported complete (DPWH). Contractor on record: MONTAÑO CONST. Figures trace to dpwh.

Region IX, Region IX
Region: Region IX

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2017 GAA. DBM GAA FY2017

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

158 projects · ₱10.6B total · 0 flags

4. Implementation

Contract Amount

₱143,443,937.46

Progress

Reported complete (DPWH)

Start Date

April 25, 2017

Target End

April 19, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.