GAA 2025 DA FMR25EF0109

CONCRETING OF BRGY. SAMARIÑANA FMR, BRGY. SAMARIÑANA, BROOJKE'S POINT, PALAWAN

CONCRETING OF BRGY. SAMARIÑANA FMR, BRGY. SAMARIÑANA, BROOJKE'S POINT, PALAWAN is a DPWH-tracked public work in Palawan 2nd DEO, Region IV-B. Reported contract value: ₱14,924,885.70. Status: Reported complete (DPWH). Contractor on record: DIANE CONST. Figures trace to dpwh.

Palawan 2nd DEO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱35,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure, Tarampitao Point, Rizal, Palawan
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Palawan 2nd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

14 projects · ₱102.3M total · 0 flags

4. Implementation

Contract Amount

₱14,924,885.70

Progress

Reported complete (DPWH)

Start Date

April 11, 2025

Target End

July 9, 2025

5. Audit