Flood Control and Drainage24CF0115

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - REHABILITATION OF BABY DAM, CABANATUAN CITY, NUEVA ECIJA

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - REHABILITATION OF BABY DAM, CABANATUAN CITY, NUEVA ECIJA is a DPWH-tracked public work in Nueva Ecija 2nd DEO, Region III. Reported contract value: ₱9,799,999.10. Status: Reported complete (DPWH). Contractor on record: CELSO C FERRER CONST CORP. Figures trace to dpwh.

Nueva Ecija 2nd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱6,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structures Slope protection / Drainage Canal, Brgy. Lusok, Bongabon, Nueva Ecija
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Nueva Ecija 2nd DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱9,799,999.10

Progress

Reported complete (DPWH)

Start Date

May 20, 2024

Target End

August 5, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.