Roads20FA0047

CLUSTER 26-WIDENING AND CONCRETING OF BANAO-BICAL ROAD, BACACAY AND STO. DOMINGO, ALBAY AND REHAB. OF PAWA-TULIW-LABNIG-ESTANCIA-PARAPUTO ROAD, MALINAO AND TABACO CITY, ALBAY

CLUSTER 26-WIDENING AND CONCRETING OF BANAO-BICAL ROAD, BACACAY AND STO. DOMINGO, ALBAY AND REHAB. OF PAWA-TULIW-LABNIG-ESTANCIA-PARAPUTO ROAD, MALINAO AND TABACO CITY, ALBAY is a DPWH-tracked public work in Albay 1st DEO, Region V. Reported contract value: ₱29,400,000.00. Status: Reported complete (DPWH). Contractor on record: JORMAND CONST. Figures trace to dpwh.

Albay 1st DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Flood Mitigation and River Control at Tagas River traversing Brgys. Baranghawon, Cobo, Basud, Tagas, Sto. Cristo and San Roque, Tabaco City, Albay
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Albay 1st DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

4. Implementation

Contract Amount

₱29,400,000.00

Progress

Reported complete (DPWH)

Start Date

December 29, 2020

Target End

July 29, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.