Flood Control and Drainage25EE0038

CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG BATO BRIDGE, TAYTAY, PALAWAN

CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG BATO BRIDGE, TAYTAY, PALAWAN is a DPWH-tracked public work in Palawan 1st DEO, Region IV-B. Reported contract value: ₱29,914,293.93. Status: Past target date (DPWH On-Going). Contractor on record: AQUALINE CONST CORP FORMERLY: AQUALINE CONST. Figures trace to dpwh.

Palawan 1st DEO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Iraan River Downstream, Brgy. Poblacion, Aborlan, Palawan
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Palawan 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

245 projects · ₱18.1B total · 0 flags

4. Implementation

Contract Amount

₱29,914,293.93

Progress

Past target date (DPWH On-Going)

Start Date

March 18, 2025

Target End

September 7, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.