Roads18HI0039

CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS-CONSTRUCTION OF DRAINAGE STRUCTURE ALONG CNHWR: K0037+301 - K0038+877, K0039+800 - K0040+178, K0040+700 - K0041+000 DANAO CITY AND CARMEN, CEBU

CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS-CONSTRUCTION OF DRAINAGE STRUCTURE ALONG CNHWR: K0037+301 - K0038+877, K0039+800 - K0040+178, K0040+700 - K0041+000 DANAO CITY AND CARMEN, CEBU is a DPWH-tracked public work in Cebu 5th DEO, Region VII. Reported contract value: ₱73,286,602.17. Status: Reported complete (DPWH). Contractor on record: VEN RAY CONST CORP. Figures trace to dpwh.

Cebu 5th DEO, Region VII
Region: Region VII

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Flood Control and Mitigation Structure along Maomaoan River, Brgy. Bonbon, Cebu City
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROV-18-0026083

₱469,427.00 · FY2018

Released to Sto. Tomas National High De School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱73,286,602.17

Progress

Reported complete (DPWH)

Start Date

April 30, 2018

Target End

March 30, 2019

5. Audit