Flood Control and Drainage20KL0038

CONSTRUCTION OF FLOOD CONTROL (UPSTREAM & DOWNSTREAM) ALONG AMOROS BRIDGE, MISAMIS ORIENTAL

CONSTRUCTION OF FLOOD CONTROL (UPSTREAM & DOWNSTREAM) ALONG AMOROS BRIDGE, MISAMIS ORIENTAL is a DPWH-tracked public work in Misamis Oriental 2nd DEO, Region X. Reported contract value: ₱49,000,000.00. Status: Reported complete (DPWH). Contractor on record: EQUI-PARCO CONST CO. Figures trace to dpwh.

Misamis Oriental 2nd DEO, Region X
Region: Region X

Money Trail

1. Appropriation

Probable match · score 98%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control (Upstream & Downstream) along Amoros Bridge, Misamis Oriental
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Misamis Oriental 2nd DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

725 projects · ₱77.9B total · 5 flags

4. Implementation

Contract Amount

₱49,000,000.00

Progress

Reported complete (DPWH)

Start Date

February 7, 2020

Target End

October 3, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.