Roads22DD0238

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), INTERJURISDICTIONAL ROADS AND/OR BRIDGES (OR, ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS), REHABILITATION OF ROAD IN BARANGAY CONCEPCION, BATANGAS CITY GOING TO BARANGAY BAGO

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), INTERJURISDICTIONAL ROADS AND/OR BRIDGES (OR, ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS), REHABILITATION OF ROAD IN BARANGAY CONCEPCION, BATANGAS CITY GOING TO BARANGAY BAGO is a DPWH-tracked public work in Batangas 4th DEO, Region IV-A. Reported contract value: ₱5,281,650.00. Status: Reported complete (DPWH). Contractor on record: LUCKY EIGHTY-THREE CONST AND SUPPLY FOR VRP. Figures trace to dpwh.

Batangas 4th DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction/Rehabilitation of Flood Mitigation Structures protecting Public Infrastructures/ Facilities at Barangay Quezon, Lipa City, Batangas
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Batangas 4th DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

132 projects · ₱845.9M total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF MULTI-PURPOSE BUILDING (PUBLIC MARKET PHASE II) AT BARANGAY TAYSAN, SAN JOSE, BATANGAS

Batangas 4th DEO, Region IV-A

2018₱28.1M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM -BASIC INFRASTRUCTURE PROGRAM (BIP)- MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES- CONSTRUCTION OF THE MULTI-PURPOSE BUILDING, BARANGAY 4, CALATAGAN, BATANGAS

Batangas 1st DEO, Region IV-A

2024₱19.8M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS, CONSTRUCTION OF AS-IS-NIYUGAN ECOTOURISM ROAD LEADING TO LAUREL TOURISM SPOTS AND TAAL VOLCANO, LAUREL, BATANGAS

Batangas 3rd DEO, Region IV-A

2022₱19.6M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROG -BASIC INFRASTRUCTURE PROG (BIP)- MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES- COMPLETION OF THE MULTI-PURPOSE BUILDING (MUNICIPAL BUILDING NORTH WING), BARANGAY CARSUCHE, TAAL, BATANGAS (PHASE 2)

Batangas 1st DEO, Region IV-A

2024₱19.2M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD CONNECTING BARANGAY SAN JOSE-BARANGAY STA. ANA A

Batangas 2nd DEO, Region IV-A

2024₱14.8M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM -BASIC INFRASTRUCTURE PROGRAM (BIP)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY BALANGA, LEMERY, BATANGAS

Batangas 1st DEO, Region IV-A

2024₱14.8M
Reported complete (DPWH)
View all 132 projects →

4. Implementation

Contract Amount

₱5,281,650.00

Progress

Reported complete (DPWH)

Start Date

April 4, 2022

Target End

May 20, 2022

5. Audit