Buildings and Facilities18DD0663

CONSTRUCTION OF MULTI-PURPOSE BUILDING (PUBLIC MARKET PHASE II) AT BARANGAY TAYSAN, SAN JOSE, BATANGAS

CONSTRUCTION OF MULTI-PURPOSE BUILDING (PUBLIC MARKET PHASE II) AT BARANGAY TAYSAN, SAN JOSE, BATANGAS is a DPWH-tracked public work in Batangas 4th DEO, Region IV-A. Reported contract value: ₱28,081,500.00. Status: Reported complete (DPWH). Contractor on record: LUCKY EIGHTY-THREE CONST AND SUPPLY FOR VRP. Figures trace to dpwh.

Batangas 4th DEO, Region IV-A
Region: Region IV-A

Follow the peso

1 of 5 steps linked to this project, 2 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2018 · ₱10,000 (shared by many projects, not this project's own line)

    Possible match · score 0.83

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-BMB-B-18-0016454 · ₱15,000,000 · release to the district office, not itemized per project

    Possible match · score 0.78

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 18DD0663 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2016-04-18 → 2025-08-03

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF MULTI-PURPOSE BUILDING (PUBLIC MARKET PHASE II) AT BARANGAY TAYSAN, SAN JOSE, BATANGAS

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Slope Protection/Revetment at Abung Br., San Juan, Batangas
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-B-18-0016454

₱15,000,000.00 · FY2018

Released to Regional Office - IVA (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

132 projects · ₱845.9M total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM -BASIC INFRASTRUCTURE PROGRAM (BIP)- MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES- CONSTRUCTION OF THE MULTI-PURPOSE BUILDING, BARANGAY 4, CALATAGAN, BATANGAS

Batangas 1st DEO, Region IV-A

2024₱19.8M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS, CONSTRUCTION OF AS-IS-NIYUGAN ECOTOURISM ROAD LEADING TO LAUREL TOURISM SPOTS AND TAAL VOLCANO, LAUREL, BATANGAS

Batangas 3rd DEO, Region IV-A

2022₱19.6M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROG -BASIC INFRASTRUCTURE PROG (BIP)- MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES- COMPLETION OF THE MULTI-PURPOSE BUILDING (MUNICIPAL BUILDING NORTH WING), BARANGAY CARSUCHE, TAAL, BATANGAS (PHASE 2)

Batangas 1st DEO, Region IV-A

2024₱19.2M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM -BASIC INFRASTRUCTURE PROGRAM (BIP)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY BALANGA, LEMERY, BATANGAS

Batangas 1st DEO, Region IV-A

2024₱14.8M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD CONNECTING BARANGAY SAN JOSE-BARANGAY STA. ANA A

Batangas 2nd DEO, Region IV-A

2024₱14.8M
Reported complete (DPWH)
No sat.

LOCAL PROGRAM, LOCAL INFRASTRUCTURE PROGRAM, LOCAL ROADS AND BRIDGES, LOCAL ROADS, A.) CONCRETING OF ROAD, BRGY. BUKAL, PADRE GARCIA, BATANGAS B.) REHABILITATION OF ROAD, TAMAK, PADRE GARCIA, BATANGAS C.) ROAD CONCRETING, BRGY. SAN MIGUEL, PADRE GARCIA, B

Batangas 4th DEO, Region IV-A

2018₱14.7M
Reported complete (DPWH)
View all 132 projects →

4. Implementation

Contract Amount

₱28,081,500.00

Progress

Reported complete (DPWH)

Start Date

October 24, 2018

Target End

April 21, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region IV-A (CALABARZON)BatangasCity of LipaMarauoy
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.