Buildings and Facilities18CI0094

COMPLETE CONSTRUCTION OF 4-STOREY 20 CLASSROOM SCHOOL BUILDING, TALIMUNDOK ELEMENTARY SCHOOL, MABALACAT CITY

COMPLETE CONSTRUCTION OF 4-STOREY 20 CLASSROOM SCHOOL BUILDING, TALIMUNDOK ELEMENTARY SCHOOL, MABALACAT CITY is a DPWH-tracked public work in Pampanga 3rd DEO, Region III. Reported contract value: ₱41,174,231.17. Status: Reported complete (DPWH). Contractor on record: ALL EML CONST CORP FORMERLY: E M L CONST. Figures trace to dpwh.

Pampanga 3rd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction /Maintenance of Flood Mitigation Structures and Drainage System, Slope Protection works along Sapangbalen Creek, Brgy. Bundagul and Paralayunan, Mabalacat City, Pampanga
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIII-18-0008955

₱0.00 · FY2018

Released to Division of Pampanga (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

66 projects · ₱3.2B total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF BY-PASS AND DIVERSION ROADLUCBAN DIVERSION RD, QUEZON

Region IV-A, Region IV-A

2025₱327.6M
Past target date (DPWH On-Going)
No sat.

NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BYPASS AND DIVERSION ROADS, BACOLOR-PORAC ACCESS ROAD (PORAC SECTION)-PACKAGE 2, PROVINCE OF PAMPANGA

Region III, Region III

2023₱162.4M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG); ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATIGIC PUBLIC BUILDINGS/FACILITIES; CONSTRUCTION OF ABACAN ROAD DIKE (LEFT SIDE) UPSTREAM OF HENSONVILLE BRIDGE, ANGELES

Pampanga 3rd DEO, Region III

2024₱130.3M
Reported complete (DPWH)
No sat.

ASSET PRESERVATION PROGRAM- PREVENTIVE MAINTENANCE - PRIMARY ROADS - JOSE ABAD SANTOS AVE (JASA) K0076+(-010)-K0077+920

Pampanga 2nd DEO, Region III

2025₱124.2M
Reported complete (DPWH)
No sat.

FY 2024 DPWH INFRASTRUCTURE PROG.-ORGANIZATIONAL OUTCOME 1:ENSURE SAFE & RELIABLE NATL ROAD SYSTEM-ASSET PRESERVATION PROG.-CONSTRUCTION / UPGRADING / REHABILITATION OF DRAINAGE ALONG NATIONAL RDS - PRIMARY RDS-DAANG MAHARLIKA (LZ)-K0088+910-K0090+042

Region IV-A, Region IV-A

2024₱114.1M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG); ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATIGIC PUBLIC BUILDINGS/FACILITIES; CONSTRUCTION OF ROAD DIKE WITH SLOPE PROTECTION ALONG ABACAN RIVER AT BARANGAY ANUNA

Pampanga 3rd DEO, Region III

2024₱96.5M
Reported complete (DPWH)
View all 66 projects →

4. Implementation

Contract Amount

₱41,174,231.17

Progress

Reported complete (DPWH)

Start Date

June 25, 2018

Target End

March 21, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.