GAA 2017 MFO-117DD0021

OFF-CARRIAGEWAY IMPROVEMENT INCLUDING DRAINAGE, TERTIARY ROADS, SAN JUAN - LAIYA ROAD, SAN JUAN, BATANGAS

OFF-CARRIAGEWAY IMPROVEMENT INCLUDING DRAINAGE, TERTIARY ROADS, SAN JUAN - LAIYA ROAD, SAN JUAN, BATANGAS is a DPWH-tracked public work in Batangas 4th DEO, Region IV-A. Reported contract value: ₱90,710,000.00. Status: Reported complete (DPWH). Contractor on record: JASMIG CONST CORP FORMERLY: JASMIG CONST SUPPLY. Figures trace to dpwh.

Batangas 4th DEO, Region IV-A
Region: Region IV-A

Follow the peso

3 of 5 steps linked from public records. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2017 · ₱25,000

    Possible match · score 0.81

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-BMB-E-17-0020346 · ₱409,941

    Possible match · score 0.60

    DBM release source ↗
  3. 3. PhilGEPS award

    Not yet linked

  4. 4. DPWH progress + satellite

    100% reported · imagery 2014-04-30 → 2025-05-12

    Same record (DPWH contract ID)

    DPWH source ↗
  5. 5. COA audit finding

    Not yet linked

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction/Improvement of Revetment with Floodwall along Downstream of Ibaan River, Ibaan, Batangas
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-E-17-0020346

₱409,941.00 · FY2017

Released to Regional Office - IV (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

373 projects · ₱15.3B total · 0 flags

4. Implementation

Contract Amount

₱90,710,000.00

Progress

Reported complete (DPWH)

Start Date

March 6, 2017

Target End

January 29, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.