Bridges16IA0019

REPLACEMENT OF PERMANENT WEAK BRIDGES, BANLAS BRIDGE ALONG MARIPIPI CIRCUMFERENTIAL ROAD, MARIPIPI, BILIRAN PROVINCE

REPLACEMENT OF PERMANENT WEAK BRIDGES, BANLAS BRIDGE ALONG MARIPIPI CIRCUMFERENTIAL ROAD, MARIPIPI, BILIRAN PROVINCE is a DPWH-tracked public work in Biliran DEO, Region VIII. Reported contract value: ₱8,301,136.88. Status: Reported complete (DPWH). Contractor on record: LEDA CONST INC. Figures trace to dpwh.

Biliran DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱8,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Bagongbong Flood Control (Revetment) along Biliran Circumferential Road, Phase II, Almeria, Biliran Province
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-16-0026880

₱0.00 · FY2016

Released to Catubig Valley National High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

181 projects · ₱9.4B total · 0 flags

4. Implementation

Contract Amount

₱8,301,136.88

Progress

Reported complete (DPWH)

Start Date

March 22, 2016

Target End

July 29, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.