Flood Control and Drainage17CC0210

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES & DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG BOCAUE RIVER K003+593.60 - K003+850 BUNLO, BOCAUE, BULACAN

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES & DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG BOCAUE RIVER K003+593.60 - K003+850 BUNLO, BOCAUE, BULACAN is a DPWH-tracked public work in Bulacan 1st DEO, Region III. Reported contract value: ₱23,273,133.59. Status: Reported complete (DPWH). Contractor on record: 525 CONST. Figures trace to dpwh.

Bulacan 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures along Bocaue River, K003+593.60 - K003+850, Bunlo, Bocaue, Bulacan
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-17-0018299

₱289,925.00 · FY2017

Released to Regional Office - IV (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱23,273,133.59

Progress

Reported complete (DPWH)

Start Date

November 20, 2017

Target End

March 19, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.