Roads25DK0100

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS - LUCBAN DIVERSION RD K0131+157 - K0132+300

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS - LUCBAN DIVERSION RD K0131+157 - K0132+300 is a DPWH-tracked public work in Quezon 1st DEO, Region IV-A. Reported contract value: ₱48,402,200.00. Status: Past target date (DPWH On-Going). Contractor on record: WAYCON BUILDERS AND CONST SUPPLY CORP FOR:WAYCON BUILDERS. Figures trace to dpwh.

Quezon 1st DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures at Barangay Daungan, Pagbilao, Quezon
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Quezon 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

474 projects · ₱22.2B total · 0 flags

4. Implementation

Contract Amount

₱48,402,200.00

Progress

Past target date (DPWH On-Going)

Start Date

June 11, 2025

Target End

August 18, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.