Buildings and Facilities17EH0047

CONSTRUCTION OF MULTI - PURPOSE CENTER, BRGY. BUDIONG, ODIONGAN, ROMBLON

CONSTRUCTION OF MULTI - PURPOSE CENTER, BRGY. BUDIONG, ODIONGAN, ROMBLON is a DPWH-tracked public work in Romblon DEO, Region IV-B. Reported contract value: ₱1,920,189.93. Status: Reported complete (DPWH). Contractor on record: PABLO S LABASBAS CONST CORP FORMERLY: PABLOS LABASBAS CONST CORP. Figures trace to dpwh.

Romblon DEO, Region IV-B
Region: Region IV-B

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2017 GAA. DBM GAA FY2017

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-17-0001876

₱7,524.00 · FY2017

Released to University of Eastern Philippines (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

515 projects · ₱13.3B total · 0 flags

Other projects by this contractor

No sat.

SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, BRGY. SUROK - GAHOY - SAPAO, GUIUAN, EASTERN SAMAR

Region VIII, Region VIII

2023₱144.5M
Past target date (DPWH On-Going)
No sat.

NETWORK DEVELOPMENT - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS TACLOBAN - STA. FE - SAN MIGUEL ROAD, LEYTE

Region VIII, Region VIII

2023₱143.5M
Past target date (DPWH On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF SHORELINE PROTECTION STRUCTURE ALONG ASUNCION - BENIT SECTION, MALITBOG, SOUTHERN LEYTE

Southern Leyte 1st DEO, Region VIII

2024₱120.5M
Past target date (DPWH On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY NUEVA ESPERANZA, HINUNANGAN, SOUTHERN LEYTE

Southern Leyte 2nd DEO, Region VIII

2025₱105.6M
Past target date (DPWH On-Going)
No sat.

ROAD WIDENING SECONDARY ROADS, WRIGHT - TAFT - BORONGAN RD (SM00172SM)K0875+667 - K0876+511, K0877+525 - K0878+256, K0878+800 - K0879+389

Eastern Samar DEO, Region VIII

2025₱104.8M
Past target date (DPWH On-Going)
No sat.

ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - TERTIARY ROADS - BAGAHUPI - BABATNGON - STA CRUZ - BARUGO - CARIGARA RD. - (S00066LT) K0927+(-348) - K0927+(-310), LEYTE 1ST LD

Region VIII, Region VIII

2023₱101.2M
Reported complete (DPWH)
View all 515 projects →

4. Implementation

Contract Amount

₱1,920,189.93

Progress

Reported complete (DPWH)

Start Date

April 25, 2017

Target End

August 7, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.