Rehabilitation / Major Repair of Flood Control Structure24CD0107

Rehabilitation of Flood Control Structure along Meycauayan River, Barangay Tawiran to Wawang Pulo, Sta. 02+356 - Sta. 02+496, Obando, Bulacan

Rehabilitation of Flood Control Structure along Meycauayan River, Barangay Tawiran to Wawang Pulo, Sta. 02+356 - Sta. 02+496, Obando, Bulacan is a DPWH-tracked public work in OBANDO (BULACAN), BULACAN, Region III. Reported contract value: ₱96,499,819.35. Status: Reported complete (DPWH). Contractor on record: EDFROBON CONST SERVICES INC. Figures trace to sumbong.

OBANDO (BULACAN), BULACAN, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 90%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Balagtas River, Barangay San Juan, Purok 4 - Purok 5, Balagtas, Bulacan
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-24-0006660

₱9,979,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0007287

₱1,460,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0000163

₱1,078,312.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0007288

₱135,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0016339

₱108,080.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

19 projects · ₱1.6B total · 0 flags

Other projects by this contractor

No sat.

LOCAL PROGRAM-NATIONAL BLDG. PROGRAM-BLDGS, & OTHER STRUCTURES-MULTI-PURPOSE/FACILITIES-CONST. OF BLDS. FOR VIROLOGY INSTITUTE OF SCIENCE AND TECHNOLOGY OF THE PHILS. (VIP), NEW CLARK CITY, CLARK FREEPORT & SPL. ECONOMIC ZONE (CFEZ), CAPAS, TARLAC

Region III, Region III

2023₱236.5M
Past target date (DPWH On-Going)
No sat.

LOCAL PROGRAM-NATIONAL BLDG. PROGRAM-BLDGS. & OTHER STRUCTURES-MULTI-PURPOSE/FACILITIES-CONST. OF BLDG. FOR VIROLOGY INSTITUTE OF SCIENCE AND TECH. OF THE PHILIPPINES (VIP), NEW CLARK CITY, CLARK FREEPORT AND SPECIAL ECONOMIC ZONE (CFEZ), CAPAS, TARLAC.

Region III, Region III

2022₱142.6M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE & SPECIAL SUPPORT PROGRAM-CONST./IMPR'VT. OF VARIOUS INFRASTRUCTURE IN SUPPORT OF NATIONAL SECURITY-CONST. OF ARMY LEADERSHIP DEV'T. & EDUCATION CENTER (ALDEC) PHASE I-TRADOC MPB, TRADOC, PA, CAMP O'DONNEL, CAPAS, TARLAC, PROV. OF TARLAC

Region III, Region III

2020₱117.6M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, LUBAO-GUAGUA-MINALIN-STO. TOMAS ROAD (LUBAO-GUAGUA SECTION)-PACKAGE 5, PROVINCE OF PAMPANGA

Region III, Region III

2022₱99.4M
Reported complete (DPWH)

FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF FLOOD CONTROL STRUCTURE, SAN MIGUEL RIVER, BARANGAY SAN JUAN, SAN MIGUEL, BULACAN, PACKAGE I

Region III, Region III

2024₱96.5M
Reported complete (DPWH)

Construction of Riverwall (Phase II) along Sacobia River, Barangay Calumpang, Mabalacat City, Pampanga

MABALACAT CITY (PAMPANGA), PAMPANGA, Region III

2024₱96.5M
Reported complete (DPWH)
View all 19 projects →

4. Implementation

Contract Amount

₱96,499,819.35

Progress

Reported complete (DPWH)

Start Date

June 5, 2024

Target End

January 11, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.