Flood Control and Drainage23IM0105

REHABILITATION OF FLOOD CONTROL STRUCTURE ALONG BURAYAN RIVER BRGY. 81, MARASBARAS, TACLOBAN CITY

REHABILITATION OF FLOOD CONTROL STRUCTURE ALONG BURAYAN RIVER BRGY. 81, MARASBARAS, TACLOBAN CITY is a DPWH-tracked public work in Tacloban City DEO, Region VIII. Reported contract value: ₱34,261,446.96. Status: Past target date (DPWH On-Going). Contractor on record: VIGUZ CONST CORP. Figures trace to dpwh.

Tacloban City DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Probable match · score 95%

UACS
18001
Amount
₱35,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Control Structure along Burayan River, Brgy. 81, Marasbaras, Tacloban City
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Tacloban City DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱34,261,446.96

Progress

Past target date (DPWH On-Going)

Start Date

August 29, 2023

Target End

April 8, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.