Roads15CD0277

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF ROADS, BRGY. STO. CRISTO,SAN JOSE DEL MONTE CITY,BULACAN

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF ROADS, BRGY. STO. CRISTO,SAN JOSE DEL MONTE CITY,BULACAN is a DPWH-tracked public work in Bulacan 2nd DEO, Region III. Reported contract value: ₱18,809,227.84. Status: Reported complete (DPWH). Contractor on record: M S RAMOS CONST INC FORMERLY: M S RAMOS. Figures trace to dpwh.

Bulacan 2nd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱49,940,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures, Sto. Cristo River, San Jose del Monte City Lone District, Bulacan, Sta. 0+497 - Sta. 0+997
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Agency-level releases for FY2016, not tied to this contract

Bulacan 2nd DEO · SARO 2,111 (₱111,347,307,043.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱18,809,227.84

Progress

Reported complete (DPWH)

Start Date

February 16, 2016

Target End

July 14, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.