Roads23E00035

CONSTRUCTION OF MISSING LINKS/NEW ROADS VICTORIA-SABLAYAN ROAD (MINDORO CROSS ISLAND ROAD), PACKAGE II, MINDORO ORIENTAL

CONSTRUCTION OF MISSING LINKS/NEW ROADS VICTORIA-SABLAYAN ROAD (MINDORO CROSS ISLAND ROAD), PACKAGE II, MINDORO ORIENTAL is a DPWH-tracked public work in Region IV-B, Region IV-B. Reported contract value: ₱187,016,116.93. Status: Past target date (DPWH On-Going). Contractor on record: STX ENT. Figures trace to dpwh.

Region IV-B, Region IV-B
Region: Region IV-B

Follow the peso

1 of 5 steps linked to this project. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    No GAA line found for this project's office and year. The GAA lists budgets by program and office, not always by project.

  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 23E00035 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    0% reported · imagery 2016-02-14 → 2016-02-14

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF MISSING LINKS/NEW ROADS VICTORIA-SABLAYAN ROAD (MINDORO CROSS ISLAND ROAD), PACKAGE II, MINDORO ORIENTAL

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2023 GAA. DBM GAA FY2023

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

129 projects · ₱11.2B total · 0 flags

4. Implementation

Contract Amount

₱187,016,116.93

Progress

Past target date (DPWH On-Going)

Start Date

March 11, 2023

Target End

March 4, 2024

5. Audit