Buildings and Facilities17AI0574

CONSTN OF TWO STRY FOUR CL SB CABITNONGAN E/S, SAN NICOLAS, PANGASINAN

CONSTN OF TWO STRY FOUR CL SB CABITNONGAN E/S, SAN NICOLAS, PANGASINAN is a DPWH-tracked public work in Pangasinan 3rd DEO, Region I. Reported contract value: ₱9,522,937.20. Status: Reported complete (DPWH). Contractor on record: ROGENOX CONST AND SUPPLY CORP. Figures trace to dpwh.

Pangasinan 3rd DEO, Region I
Region: Region I

Follow the peso

2 of 5 steps linked to this project, 2 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2017 · ₱5,000 (shared by many projects, not this project's own line)

    Possible match · score 0.84

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-ROXI-17-0020284 · ₱2,411,974 · release to the district office, not itemized per project

    Possible match · score 0.66

    DBM release source ↗
  3. 3. PhilGEPS award

    ₱9,522,937 · ROGENOX CONST AND SUPPLY CORP

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    100% reported · imagery 2014-02-16 → 2020-11-18

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Unit-cost benchmark · School building, cost per classroom (new school building)

₱2,380,734 per classroom= 1.4x the Region I median (n=898)

Contract cost ₱9,522,937 ÷ 4 classroom read from the DPWH title (“FOUR CL”; classroom count in title). National percentile: 75. Higher unit cost can have legitimate causes (terrain, design, scope not stated in the title); this is a comparison, not a finding. Methodology

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTN OF TWO STRY FOUR CL SB CABITNONGAN E/S, SAN NICOLAS, PANGASINAN

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Agno River Basin and Allied Rivers Flood Control Project-Construction of Bank Protection, Brgy. Camangaan, San Nicolas, Pangasinan
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXI-17-0020284

₱2,411,974.00 · FY2017

Released to University of Southeastern Philippines (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱9,522,937.20

Progress

Reported complete (DPWH)

Start Date

December 21, 2017

Target End

May 29, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region I (Ilocos Region)PangasinanSan NicolasCabitnongan
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.