Bridges23IB0050

REHABILITATION/ MAJOR REPAIR OF PERMANENT BRIDGES (INSTALLATION OF CARON FIBER) SURIBAO BR. (B00479SM) ALONG BORONGAN - GUIUAN ROAD

REHABILITATION/ MAJOR REPAIR OF PERMANENT BRIDGES (INSTALLATION OF CARON FIBER) SURIBAO BR. (B00479SM) ALONG BORONGAN - GUIUAN ROAD is a DPWH-tracked public work in Eastern Samar DEO, Region VIII. Reported contract value: ₱72,374,993.00. Status: Reported complete (DPWH). Contractor on record: WYNE ROSE CONST AND SUPPLY CORP. Figures trace to dpwh.

Eastern Samar DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Barangay Poblacion, Hernani, Eastern Samar
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Eastern Samar DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

23IB0050 - Rehabilitation/Major Repair of Permanen

₱72,319,468.00 · P.B. OBIAL CONSTRUCTION

Contractor

26 projects · ₱564.6M total · 0 flags

Other projects by this contractor

View all 26 projects →

4. Implementation

Contract Amount

₱72,374,993.00

Progress

Reported complete (DPWH)

Start Date

March 21, 2023

Target End

January 24, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.