Construction of Flood Mitigation Structure23I00143

Construction of Subang Daku Flood Control (San Isidro Section), Sogod, Southern Leyte

Construction of Subang Daku Flood Control (San Isidro Section), Sogod, Southern Leyte is a DPWH-tracked public work in SOGOD (SOUTHERN LEYTE), SOUTHERN LEYTE, Region VIII. Reported contract value: ₱19,299,932.00. Status: Reported complete (DPWH). Contractor on record: JUCONS CONST OPC FORMERLY:JUCONS CONST &SUPPLY. Figures trace to sumbong.

SOGOD (SOUTHERN LEYTE), SOUTHERN LEYTE, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Probable match · score 90%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures in Barangay Bato 1 to 2, Maasin City, Southern Leyte
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Southern Leyte 2nd District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

106 projects · ₱4.2B total · 0 flags

Other projects by this contractor

1. CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY BURABUD-AN, ABUYOG, LEYTE; 2. CONSTRUCTION OF FLOOD CONTROL STRUCTURE CADAC-AN RIVER, BARANGAY PAGSANG-AN, ABUYOG, LEYTE

Region VIII, Region VIII

2024₱294.9M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF MISSING LINKS/NEW ROADS, LILOAN - SAN RICARDO CIRCUMFERENTIAL ROAD, SOUTHERN LEYTE

Region VIII, Region VIII

2024₱271.5M
Past target date (DPWH On-Going)
No sat.

CLUSTER 11: 1. SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF (RCDG) REINFORCED CONCRETE DECK GIRDER BRIDGE BARAN

Region VIII, Region VIII

2024₱225.7M
Past target date (DPWH On-Going)
No sat.

SIPAG - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF SEAWALL PROTECTION ALONG THE SHORELINES OF BRGY. BITO, BARANGAY GUINTAGBACAN, BARANGAY BUNGA AND BARANGAY SAN ISIDRO, ABUYOG, LEYTE

Region VIII, Region VIII

2024₱193.0M
Past target date (DPWH On-Going)
No sat.

SIPAG - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF SEAWALL PROTECTION ALONG THE SHORELINES OF BRGY. NALIBUNAN, BARANGAY LOYONSAWANG, AND BARANGAY BUNTAY, ABUYOG, LEYTE

Region VIII, Region VIII

2024₱192.9M
Past target date (DPWH On-Going)
No sat.

SIPAG - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES - CONSTRUCTION OF SEAWALL PROTECTION ALONG THE SHORELINES OF BRGY. STO, NIÑO, BARANGAY STA. FE, AND BARANGAY VICTORY, ABUYOG, LEYTE

Region VIII, Region VIII

2024₱192.5M
Past target date (DPWH On-Going)
View all 106 projects →

4. Implementation

Contract Amount

₱19,299,932.00

Progress

Reported complete (DPWH)

Start Date

September 11, 2023

Target End

March 28, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.