GAA 2024 SSP24I00261

CLUSTER 11: 1. SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF (RCDG) REINFORCED CONCRETE DECK GIRDER BRIDGE BARAN

CLUSTER 11: 1. SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF (RCDG) REINFORCED CONCRETE DECK GIRDER BRIDGE BARAN is a DPWH-tracked public work in Region VIII, Region VIII. Reported contract value: ₱225,728,790.46. Status: Past target date (DPWH On-Going). Contractor on record: JUCONS CONST OPC FORMERLY:JUCONS CONST &SUPPLY. Figures trace to dpwh.

Region VIII, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2024 GAA. DBM GAA FY2024

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

106 projects · ₱4.2B total · 0 flags

Other projects by this contractor

1. CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY BURABUD-AN, ABUYOG, LEYTE; 2. CONSTRUCTION OF FLOOD CONTROL STRUCTURE CADAC-AN RIVER, BARANGAY PAGSANG-AN, ABUYOG, LEYTE

Region VIII, Region VIII

2024₱294.9M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF MISSING LINKS/NEW ROADS, LILOAN - SAN RICARDO CIRCUMFERENTIAL ROAD, SOUTHERN LEYTE

Region VIII, Region VIII

2024₱271.5M
Past target date (DPWH On-Going)
No sat.

SIPAG - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF SEAWALL PROTECTION ALONG THE SHORELINES OF BRGY. BITO, BARANGAY GUINTAGBACAN, BARANGAY BUNGA AND BARANGAY SAN ISIDRO, ABUYOG, LEYTE

Region VIII, Region VIII

2024₱193.0M
Past target date (DPWH On-Going)
No sat.

SIPAG - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF SEAWALL PROTECTION ALONG THE SHORELINES OF BRGY. NALIBUNAN, BARANGAY LOYONSAWANG, AND BARANGAY BUNTAY, ABUYOG, LEYTE

Region VIII, Region VIII

2024₱192.9M
Past target date (DPWH On-Going)
No sat.

SIPAG - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES - CONSTRUCTION OF SEAWALL PROTECTION ALONG THE SHORELINES OF BRGY. STO, NIÑO, BARANGAY STA. FE, AND BARANGAY VICTORY, ABUYOG, LEYTE

Region VIII, Region VIII

2024₱192.5M
Past target date (DPWH On-Going)
No sat.

ASET PRESERVATION - PREVENTIVE MAINTENANCE - PRIMARY ROADS - DAANG MAHARLIKA (LT) (S00223LT) - K1024+616 - K1027+060, SOUTHERN LEYTE SUB-DISTRICT

Region VIII, Region VIII

2024₱180.2M
Reported complete (100% progress, DPWH status On-Going)
View all 106 projects →

4. Implementation

Contract Amount

₱225,728,790.46

Progress

Past target date (DPWH On-Going)

Start Date

September 10, 2024

Target End

June 13, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.