Roads17PI0093

ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS -SECONDARY ROADS, DANTAY-SAGADA RD. - K0388+606 - 388 +729 (S00509LZ)

ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS -SECONDARY ROADS, DANTAY-SAGADA RD. - K0388+606 - 388 +729 (S00509LZ) is a DPWH-tracked public work in Mountain Province 1st DEO, Cordillera Administrative Region. Reported contract value: ₱4,752,160.85. Status: Reported complete (DPWH). Contractor on record: CHUWARCHO CONST. Figures trace to dpwh.

Mountain Province 1st DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱7,500,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction/Rehabilitation of Upper Calacaban Flood Control, Calacaban, Tadian, Mt. Province
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-D-18-0005195

₱229,772.00 · FY2018

Released to Central Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

8 projects · ₱97.1M total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO AIRPORTS, SEAPORTS, AND DECLARED TOURISM DESTINATIONS, BALILI-SUYO-SAGADA ROAD LEADING TO SAGADA CAVES, BURIAL CAVES, RICE TERRACES AND WATERFALLS, BONTOC AND SAGADA, MT. PROVINCE

Mountain Province 1st DEO, Cordillera Administrative Region

2016₱34.4M
Reported complete (DPWH)
No sat.

CSSP-ACCESS ROADS TO TOURISM DESTINATION, SABANGAN-SAGADA RD.

Mountain Province 1st DEO, Cordillera Administrative Region

2018₱14.3M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF MISSING LINKS/NEW ROADS, TANUDAN-BARLIG-IFUGAO ROAD, MOUNTAIN PROVINCE CHAINAGE 0-CHAINAGE 540

Mountain Province 2nd DEO, Cordillera Administrative Region

2020₱9.5M
Reported complete (DPWH)
No sat.

CSSP-SAGADA-AGUID ROAD IN SUPPORT OF COFFEE WEAVING, FOOD PROCESSING AND TOURISM INDUSTRIES, SAGADA, MOUNTAIN PROVINCE

Mountain Province 1st DEO, Cordillera Administrative Region

2020₱9.5M
Reported complete (DPWH)
No sat.

FLOOD MANAGEMENT PROGRAM-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE-CONSTRUCTION OF TANUDAN FLOOD CONTROL, BARLIG, MOUNTAIN PROVINCE

Mountain Province 2nd DEO, Cordillera Administrative Region

2020₱9.5M
Reported complete (DPWH)
No sat.

RESTORATION OF COLLAPSED REINFORCED CONCRETE RETAINING WALL ALONG SABANGAN-SAGADA ROAD LEADING TO POBLACION SAGADA, SUMAGUING CAVE, HANGING COFFINS, BOMOD-OK FALLS, BOKONG FALLS, MARCOS CAVE, SAGADA, MOUNTAIN PROVINCE

Cordillera Administrative Region, Cordillera Administrative Region

2016₱7.6M
Reported complete (DPWH)
View all 8 projects →

4. Implementation

Contract Amount

₱4,752,160.85

Progress

Reported complete (DPWH)

Start Date

April 23, 2018

Target End

June 18, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.