GAA 2017 MFO-117L00114

WIDENING (2 INTO 4 LANES) OF SURIGAO DEL SUR BDRY.-DVO. OR. COASTAL RD INCL. SLOPE PROTECTION & RROW

WIDENING (2 INTO 4 LANES) OF SURIGAO DEL SUR BDRY.-DVO. OR. COASTAL RD INCL. SLOPE PROTECTION & RROW is a DPWH-tracked public work in Region XI, Region XI. Reported contract value: ₱89,958,697.84. Status: Reported complete (DPWH). Contractor on record: MAVERICK BUILDERS INC FORMERLY MAVERICK. Figures trace to dpwh.

Region XI, Region XI
Region: Region XI

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2017 GAA. DBM GAA FY2017

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱89,958,697.84

Progress

Reported complete (DPWH)

Start Date

May 2, 2017

Target End

December 24, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.