GAA 2025 SSP25HG0092

IMPROVEMENT OF ROAD LEADING TO LAPYAHAN SA SAN REMIGIO, BRGY. POBLACION, SAN REMIGIO, CEBU

IMPROVEMENT OF ROAD LEADING TO LAPYAHAN SA SAN REMIGIO, BRGY. POBLACION, SAN REMIGIO, CEBU is a DPWH-tracked public work in Cebu 4th DEO, Region VII. Reported contract value: ₱47,991,560.95. Status: Past target date (DPWH On-Going). Contractor on record: WTG CONST. Figures trace to dpwh.

Cebu 4th DEO, Region VII
Region: Region VII

Money Trail

1. Appropriation

Possible match · score 79%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure, Brgy. Carreta , Cebu City
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Cebu 4th DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

298 projects · ₱12.8B total · 0 flags

Other projects by this contractor

CONSTRUCTION OF STORM SURGE PROTECTION: HEIGHTENED ROAD AND TIDE EMBANKMENT, STATION 1+900 - STATION 2+550, SECTION 5 PHASE 9, BRGY. SAN JOAQUIN, PALO, LEYTE

Region VIII, Region VIII

2018₱263.4M
Reported complete (DPWH)

CONSTRUCTION OF FLOOD MITIGATION FACILITIES ALONG MAJOR RIVER BASINS AND PRINCIPAL RIVERS AT SIPALAY RIVER

Region VI, Region VI

2018₱195.5M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF FLYOVERS/INTERCHANGES/UNDERPASSES/LONG SPAN BRIDGES PANGLAO-TAGBILARAN CITY OFFSHORE BRIDGE, SECTION 1: STA.000+000-STA.000+223.21, SECTION

Region VII, Region VII

2020₱193.0M
Reported complete (DPWH)
No sat.

CSSP, SUSTAINABLE INFRA PROJ. ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BLDG./ FACILITIES, CONST. OF ROAD FROM TABON TO BARANGAY GUBA LEADING TO BINAKAYAN, VALLEHERMOSO,NEGROS ORIENTAL

Region VII, Region VII

2024₱193.0M
Past target date (DPWH On-Going)
No sat.

CSSP, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG PINOCAWAN RIVER, VALLEHERMOSO, NEGROS ORIENTAL

Region VII, Region VII

2024₱193.0M
Past target date (DPWH On-Going)
No sat.

CSSP, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BATERIA RIVER, GUIHULNGAN CITY, NEGROS ORIENTAL

Region VII, Region VII

2024₱193.0M
Past target date (DPWH On-Going)
View all 298 projects →

4. Implementation

Contract Amount

₱47,991,560.95

Progress

Past target date (DPWH On-Going)

Start Date

May 19, 2025

Target End

August 22, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.