GAA 2025 SSP25MB0102

CONCRETING OF ROAD, FROM BARANGAY POBLACION TO BARANGAY CROSSING RUBBER, POBLACION, TUPI, SOUTH COTABATO

CONCRETING OF ROAD, FROM BARANGAY POBLACION TO BARANGAY CROSSING RUBBER, POBLACION, TUPI, SOUTH COTABATO is a DPWH-tracked public work in South Cotabato 1st DEO, Region XII. Reported contract value: ₱19,205,722.16. Status: Past target date (DPWH On-Going). Contractor on record: AMPLEX CONST AND SUPPLIES. Figures trace to dpwh.

South Cotabato 1st DEO, Region XII
Region: Region XII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 75%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Balite River Flood Control Structure, Barangay M. Adriatico, Gloria, Oriental Mindoro
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

South Cotabato 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

25MB0102 - Concreting of Road, from Barangay Pobla

₱19,205,722.16 · AMPLEX CONSTRUCTION AND SUPPLIES

Contractor

B

111 projects · ₱3.9B total · 0 flags

4. Implementation

Contract Amount

₱19,205,722.16

Progress

Past target date (DPWH On-Going)

Start Date

July 18, 2025

Target End

January 14, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.