Flood Control and Drainage25DN0055

CONSTRUCTION OF FLOOD CONTROL STRUCTURE, CAINTA RIVER, BARANGAY SANTO DOMINGO, CAINTA, RIZAL (FIRST DISTRICT)

CONSTRUCTION OF FLOOD CONTROL STRUCTURE, CAINTA RIVER, BARANGAY SANTO DOMINGO, CAINTA, RIZAL (FIRST DISTRICT) is a DPWH-tracked public work in Rizal 1st DEO, Region IV-A. Reported contract value: ₱28,223,638.81. Status: Past target date (DPWH On-Going). Contractor on record: F316 CONST CORP. Figures trace to dpwh.

Rizal 1st DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Probable match · score 92%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Cainta River, Barangay Santo Domingo, Cainta, Rizal
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Rizal 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

4. Implementation

Contract Amount

₱28,223,638.81

Progress

Past target date (DPWH On-Going)

Start Date

March 27, 2025

Target End

September 7, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.